Corpo Santo Hotel - Rehabilitation of Buildings at Rua do Arsenal and Largo do Corpo Santo, Lisbon

Greatcreation

Demolition, Façades Containment, Archaeological Excavation, Peripheral Containment, Structure, Finishing and Special Installations for execution of Corpo Santo Hotel:

  1. Demolition
  2. Facade Containment
  3. Excavation and Peripheral Containment
  4. Structure
  5. Finishing's
  6. Special Installations


Duration Value
22 months (several stages) 6 900 000€
()

Turism Facilities + Hotels
Urban Rehabilitation